Actions
Task #1478
openPhase #1392: Phase D: Assembly, Integration and Testing
Topic #1423: Flight Model FlatSat
Core FM FlatSat + Solar Panels + Heracles
Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
07/16/2025
Due date:
07/23/2025 (Due in 36 days)
% Done:
0%
Estimated time:
Subsystem:
Systems
Success Criteria:
tests are complete
Updated by Priya Manavalan 5 days ago
- Tracker changed from Topic to Task
- Success Criteria set to [NEEDS SUCCESS CRITERIA]
Updated by Priya Manavalan about 2 hours ago
- Due date set to 06/19/2025
- Success Criteria changed from [NEEDS SUCCESS CRITERIA] to tests are complete
Updated by Priya Manavalan about 2 hours ago
- Due date changed from 06/19/2025 to 07/23/2025
- Start date changed from 06/12/2025 to 07/16/2025
- Follows Task #1470: Core EM FlatSat + Solar Panels + Heracles added