Task #1549

open

Phase #1392: Phase D: Assembly, Integration and Testing

Topic #1547: Mission Design AIT

MOP Final Draft

Added by Priya Manavalan 12 days ago. Updated 11 days ago.

Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
07/02/2025
Due date:
08/13/2025 (Due in 38 days)
% Done:

40%

Estimated time:
Subsystem:
Mission Design
Success Criteria:
draft is done

Related issues 2 (2 open0 closed)

Follows Ex-Alta 3 - Task #1548: LEOP 2nd Draft In Progress06/24/202507/01/2025

Actions
Precedes Ex-Alta 3 - Task #1550: Orbital Operations ManualIn Progress08/15/202502/03/2026

Actions
Actions #1

Updated by Priya Manavalan 12 days ago

  • Due date changed from 08/05/2025 to 08/13/2025
  • Start date changed from 06/24/2025 to 07/02/2025
  • Follows Task #1548: LEOP 2nd Draft added
Actions #2

Updated by Priya Manavalan 12 days ago

  • Precedes Task #1550: Orbital Operations Manual added
Actions #3

Updated by Joanne Cai 11 days ago

  • % Done changed from 0 to 40

getting it reviewed section by section, whole team is working on each section