closedPhase #714: Phase A: Concept and Technology Development Activities
Feature #88: CONOPS
First Draft STM
Subsystem:
Success Criteria:
Description
Who: Priya + input from systems, mission design and Iris
What: Create a preliminary STM to start outlining mission requirements
How: Start with the mission objective, work down to the system requirements
Definition of done: Finish column A and B
Updated by Priya Manavalan about 2 years ago
- Project changed from Sprint 002 to CUBICS
Updated by Priya Manavalan about 2 years ago
- Project changed from CUBICS to Sprint 003
Updated by Priya Manavalan about 2 years ago
- Due date changed from 04/04/2023 to 04/15/2023
Updated by Priya Manavalan about 2 years ago
- Status changed from New to In Progress
Updated by Priya Manavalan about 2 years ago
- Project changed from Sprint 003 to CUBICS
Updated by Priya Manavalan about 2 years ago
- Project changed from CUBICS to Sprint 004
- Subsystem deleted (
Project Management)
Updated by Priya Manavalan almost 2 years ago
- Project changed from Sprint 004 to CUBICS
Updated by Priya Manavalan almost 2 years ago
- Status changed from In Progress to Closed