User Story #1123
closedPhase #715: Phase B: Preliminary Design and Technology Completion Activities
Epic #977: Preliminary Designs and ICDs
Feature #1031: Preliminary Design: Icarus
Preliminary Stack Volume Budget
Description
Responsible: Brandon
Accountable: Ben
Consulted: Tyler, Ben, Former Mechanical team members
Informed: Mechanical Team
What: Generate a preliminary volume budget for Ex3 stack based on tentative sub-system component selection. Reach out to ADCS, Power, OBC, DFGM and Comms. Find out what components they have tentatively selected and what components will occupy space in the stack. Sum up the total required vertical space in the stack in order to accommodate the anticipated hardware. Use ex2 volume budget for reference:
https://docs.google.com/presentation/d/1UYb-Akej6n5bjXTnwY8fOomh8HPi-_ktEn3ejOLOoF4/edit#slide=id.g4bc89b36a4_3_21
Limit your work to the allocated 200mm stack area for now. Include a contingency for each A future task will expand on this.
Why: Volume budget is a deliverable for PDR