Topic #1447

open

Phase #1392: Phase D: Assembly, Integration and Testing

Critical Hardware Binary Tests

Added by Priya Manavalan 5 days ago. Updated about 13 hours ago.

Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
06/23/2025
Due date:
08/08/2025 (Due in 51 days)
% Done:

0%

Estimated time:
(Total: 0:00 h)
Subsystem:
Systems

Subtasks 4 (4 open0 closed)

Task #1448: Power Subsystem TestingIn Progress06/27/202507/04/2025

Actions
Task #1449: UHF Transceiver + Antenna Binary TestIn Progress07/31/202508/04/2025

Actions
Task #1450: UHF Transciever + Antenna + Ground Station Binary TestsIn Progress08/05/202508/08/2025

Actions
Task #1451: S-band Transmitter + AntennaIn Progress06/23/202506/23/2025

Actions
Actions