Task #1464

open

Phase #1392: Phase D: Assembly, Integration and Testing

Topic #1460: Binary Tests w/OBC

Iris + OBC

Added by Priya Manavalan 5 days ago. Updated about 4 hours ago.

Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
06/30/2025
Due date:
07/04/2025 (Due in 17 days)
% Done:

0%

Estimated time:
Subsystem:
Systems
Success Criteria:
Test is complete

Related issues 1 (1 open0 closed)

Precedes Ex-Alta 3 - Task #1473: Iris EM FlatSat testingIn Progress07/07/202507/11/2025

Actions
Actions #1

Updated by Priya Manavalan 5 days ago

  • Parent task changed from #1392 to #1460
Actions #2

Updated by Priya Manavalan 4 days ago

  • Due date set to 06/13/2025
  • Start date changed from 06/12/2025 to 06/13/2025
  • Follows Task #1440: Iris AIT added
Actions #3

Updated by Priya Manavalan 4 days ago

  • Due date changed from 06/13/2025 to 06/30/2025
  • Start date changed from 06/13/2025 to 06/30/2025
Actions #4

Updated by Priya Manavalan about 4 hours ago

Actions #5

Updated by Priya Manavalan about 4 hours ago

  • Due date changed from 06/30/2025 to 07/04/2025
Actions #6

Updated by Priya Manavalan about 3 hours ago

  • Precedes Task #1473: Iris EM FlatSat testing added