Task #1473
openPhase #1392: Phase D: Assembly, Integration and Testing
Topic #1415: Engineering Model FlatSat
Iris EM FlatSat testing
Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
07/07/2025
Due date:
07/11/2025 (Due in 24 days)
% Done:
0%
Estimated time:
Subsystem:
Iris
Success Criteria:
tests are complete
Updated by Priya Manavalan 4 days ago
- Due date set to 06/30/2025
- Start date changed from 06/12/2025 to 06/30/2025
- Follows Task #1440: Iris AIT added
Updated by Priya Manavalan about 2 hours ago
- Follows deleted (Task #1440: Iris AIT)
Updated by Priya Manavalan about 1 hour ago
- Due date changed from 06/30/2025 to 07/04/2025
Updated by Priya Manavalan about 1 hour ago
- Due date changed from 07/04/2025 to 07/11/2025
- Start date changed from 06/30/2025 to 07/07/2025
- Follows Task #1457: Iris + EPS added
- Follows Task #1464: Iris + OBC added
Updated by Priya Manavalan about 1 hour ago
- Precedes Task #1476: Full EM FlatSat Testing added
Updated by Priya Manavalan 32 minutes ago
- Precedes Task #1481: Iris FM FlatSat Testing added