Project

General

Profile

Actions

Task #1473

open

Phase #1392: Phase D: Assembly, Integration and Testing

Topic #1415: Engineering Model FlatSat

Iris EM FlatSat testing

Added by Priya Manavalan 5 days ago. Updated about 1 hour ago.

Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
07/07/2025
Due date:
07/11/2025 (Due in 24 days)
% Done:

0%

Estimated time:
Subsystem:
Iris
Success Criteria:
tests are complete

Related issues 4 (4 open0 closed)

Follows Ex-Alta 3 - Task #1457: Iris + EPSIn Progress06/30/202507/04/2025

Actions
Follows Ex-Alta 3 - Task #1464: Iris + OBCIn Progress06/30/202507/04/2025

Actions
Precedes Ex-Alta 3 - Task #1476: Full EM FlatSat TestingIn Progress08/18/202509/18/2025

Actions
Precedes Ex-Alta 3 - Task #1481: Iris FM FlatSat TestingIn Progress07/14/202507/21/2025

Actions
Actions #1

Updated by Priya Manavalan 4 days ago

  • Due date set to 06/30/2025
  • Start date changed from 06/12/2025 to 06/30/2025
  • Follows Task #1440: Iris AIT added
Actions #3

Updated by Priya Manavalan about 2 hours ago

Actions #4

Updated by Priya Manavalan about 1 hour ago

  • Due date changed from 06/30/2025 to 07/04/2025
Actions #5

Updated by Priya Manavalan about 1 hour ago

  • Due date changed from 07/04/2025 to 07/11/2025
  • Start date changed from 06/30/2025 to 07/07/2025
  • Follows Task #1457: Iris + EPS added
  • Follows Task #1464: Iris + OBC added
Actions #6

Updated by Priya Manavalan about 1 hour ago

  • Precedes Task #1476: Full EM FlatSat Testing added
Actions #7

Updated by Priya Manavalan 32 minutes ago

  • Precedes Task #1481: Iris FM FlatSat Testing added