User Story #146
closed
CUBICS - Feature #18: ICARUS Redesign
Rail switch case study
Added by Priya Manavalan about 2 years ago.
Updated about 2 years ago.
Description
Create an explanation for how to integrate rail switches into the rails. What design constraints come with rail switches?
Determine system requirements relevant for rail switches.
There exists similar documentation from Ex-Alta 2 that could be useful. Look on the drive and/or ask Sichun.
- Priority changed from Normal to High
- Due date set to 03/21/2023
- Start date changed from 03/08/2023 to 03/07/2023
- Estimated time set to 10:00 h
Who: Newer members (2)
What: Create an explanation for how to integrate rail switches into the rails. What design constraints come with rail switches?
How: Ask Joanne
- Assignee set to Saksham Verma
- Subsystem set to Mechanical
- Project changed from 12 to CUBICS
- Project changed from CUBICS to Sprint 002
- Description updated (diff)
- Project changed from Sprint 002 to CUBICS
- Project changed from CUBICS to Sprint 003
- Status changed from New to In Progress
- % Done changed from 0 to 100
- Status changed from In Progress to Closed
Also available in: Atom
PDF