Actions
User Story #452
closedFeature #207: Iris MCR
Finalize Iris Subsystem Requirements
Subsystem:
Iris
Success Criteria:
Completed spreadsheet detailing all Iris subsystem requirements.
Description
Based on the finalized outcomes from the Science Traceability Matrix, a formal systems requirement document will need to be defined for all of Ex-Alta 3. To ensure there is clarity on Iris subsystem requirements, the Iris internal requirements document (https://docs.google.com/spreadsheets/d/1QJTZpUCyph8ICNG6fEeEjctEX02c4IdNdAtso0ZstMQ/edit#gid=182022398) should be completed in parallel with general system requirements, as soon as possible.
Responsible: @Dipesh Aggarwal, @Yeh-In Kang, @Connor McNeill
Accountable: @Dipesh Aggarwal, @Yeh-In Kang
Consult: @Elliot Saive, @Liam Droog
Inform: @Priya Manavalan, @Joanne Cai, @Pundeep Hundal
Updated by Dipesh Aggarwal almost 2 years ago
- Project changed from CUBICS to Sprint 005
Updated by Dipesh Aggarwal almost 2 years ago
- Success Criteria set to Completed spreadsheet detailing all Iris subsystem requirements.
Updated by Dipesh Aggarwal almost 2 years ago
- Project changed from Sprint 005 to CUBICS
Updated by Dipesh Aggarwal almost 2 years ago
- Due date changed from 05/30/2023 to 06/06/2023
Updated by Yeh-In Kang almost 2 years ago
- Project changed from CUBICS to Sprint 006
- % Done changed from 0 to 20
- Estimated time changed from 4:00 h to 8:00 h
Updated by Dipesh Aggarwal almost 2 years ago
- Project changed from Sprint 006 to CUBICS
Updated by Dipesh Aggarwal almost 2 years ago
- Due date changed from 06/06/2023 to 06/27/2023
Updated by Dipesh Aggarwal almost 2 years ago
- Project changed from CUBICS to Sprint 007
Updated by Dipesh Aggarwal almost 2 years ago
- Project changed from Sprint 007 to CUBICS
Updated by Dipesh Aggarwal almost 2 years ago
- Due date changed from 06/27/2023 to 07/25/2023
Updated by Yeh-In Kang almost 2 years ago
- Project changed from CUBICS to Sprint 8
- Parent task deleted (
#45) - Subsystem deleted (
Iris) - Subgroup deleted (
Iris Management)
Updated by Priya Manavalan almost 2 years ago
- Project changed from Sprint 8 to Sprint 008
- Subsystem set to Iris
Updated by Dipesh Aggarwal almost 2 years ago
- Project changed from Sprint 008 to CUBICS
Updated by Dipesh Aggarwal almost 2 years ago
- Project changed from CUBICS to Sprint 009
Updated by Yeh-In Kang almost 2 years ago
- Project changed from Sprint 009 to CUBICS
Updated by Dipesh Aggarwal almost 2 years ago
- Due date changed from 07/25/2023 to 08/08/2023
Updated by Dipesh Aggarwal almost 2 years ago
- Project changed from CUBICS to Sprint 010
Updated by Dipesh Aggarwal over 1 year ago
- Due date changed from 08/08/2023 to 08/15/2023
Updated by Dipesh Aggarwal over 1 year ago
- Project changed from Sprint 010 to CUBICS
Updated by Dipesh Aggarwal over 1 year ago
- Project changed from CUBICS to Sprint 011
Updated by Dipesh Aggarwal over 1 year ago
- Priority changed from High to Urgent
Updated by Dipesh Aggarwal over 1 year ago
- Project changed from Sprint 011 to CUBICS
Actions