closed

Northern SPIRIT - Feature #4: UHF Ground Station

UHF Ground Station Spring Inspection

Added by Thomas Ganley about 2 years ago. Updated about 2 years ago.

Status:
Closed
Priority:
High
Start date:
03/03/2023
Due date:
04/15/2023
% Done:

100%

Estimated time:
2:00 h
Spent time:
Subsystem:
Success Criteria:

Description

Who: Only those qualified to go up on the roof
What:
Why:

Planned for Tuesday April 11 (must be during work hours) -- should do while we do the camera fix for UHF rotor calibration.

  1. Make a checklist of all things that must be checked
  2. Make a Field Activities Plan
  3. Go to the roof and do an inspection following the checklist
Actions #1

Updated by Priya Manavalan about 2 years ago

  • Priority changed from Normal to High
Actions #2

Updated by Joanne Cai about 2 years ago

  • Description updated (diff)
  • Due date set to 04/15/2023
  • Estimated time set to 2:00 h
  • Subsystem set to Communications
Actions #3

Updated by Joanne Cai about 2 years ago

  • Project changed from Northern SPIRIT to Sprint 117
  • Subsystem deleted (Communications)
Actions #4

Updated by Pundeep Hundal about 2 years ago

  • % Done changed from 0 to 100
Actions #5

Updated by Pundeep Hundal about 2 years ago

  • Status changed from New to Closed