Actions
User Story #55
closedNorthern SPIRIT - Feature #4: UHF Ground Station
UHF Ground Station Spring Inspection
Subsystem:
Success Criteria:
Description
Who: Only those qualified to go up on the roof
What:
Why:
Planned for Tuesday April 11 (must be during work hours) -- should do while we do the camera fix for UHF rotor calibration.
- Make a checklist of all things that must be checked
- Make a Field Activities Plan
- Go to the roof and do an inspection following the checklist
Updated by Priya Manavalan about 2 years ago
- Priority changed from Normal to High
Updated by Joanne Cai about 2 years ago
- Description updated (diff)
- Due date set to 04/15/2023
- Estimated time set to 2:00 h
- Subsystem set to Communications
Updated by Joanne Cai about 2 years ago
- Project changed from Northern SPIRIT to Sprint 117
- Subsystem deleted (
Communications)
Actions