General

Profile

Nikhil Velagapudi

Issues

open closed Total
Assigned issues 5 9 14
Reported issues 10 10 20

Projects

Project Roles Registered on
CUBICS Team Lead, Team Member 03/01/2023
Sprint 002 Team Lead, Team Member 03/20/2023
Sprint 003 Team Lead, Team Member 04/03/2023
Sprint 004 Team Member 05/02/2023
Sprint 005 Team Lead, Team Member 05/16/2023
Sprint 006 Team Lead, Team Member 05/30/2023
Sprint 007 Team Lead, Team Member 06/13/2023
Sprint 008 Team Lead, Team Member 06/27/2023
Sprint 009 Team Lead, Team Member 07/11/2023
Sprint 010 Team Lead, Team Member 07/25/2023
Sprint 011 Team Lead, Team Member 08/08/2023
Sprint 012 Team Lead, Team Member 08/22/2023
Sprint 013 Team Lead, Team Member 09/05/2023
Sprint 014 Team Lead, Team Member 09/19/2023
Sprint 015 Team Lead, Team Member 10/03/2023
Sprint 016 Team Lead, Team Member 10/31/2023
Sprint 017 Team Lead, Team Member 11/19/2023
Sprint 018 Team Lead, Team Member 12/18/2023
Sprint 019 Team Lead, Team Member 01/09/2024
Northern SPIRIT Team Lead 02/25/2023
Sprint 116 Team Lead 03/20/2023
Sprint 117 Team Lead 04/04/2023
Sprint 118 Team Lead 04/17/2023
Sprint 119 Team Lead, Team Member 05/02/2023
Sprint 120 Team Lead 05/16/2023
Program Management Team Lead 03/05/2023

Activity

11/21/2023

11:38 PM Program Management User Story #108 (Closed): Update Steering Group Terms of Reference
Nikhil Velagapudi
11:38 PM Program Management User Story #964 (Closed): Make the Mass Model
Nikhil Velagapudi

11/08/2023

12:11 AM Program Management User Story #964 (Closed): Make the Mass Model
Thomas to make the mass model and complete it Nikhil Velagapudi

09/19/2023

10:40 PM Program Management User Story #862 (In Progress): Create MOU for AlbertaSat/STARR for Ringo 2B
Nikhil Velagapudi
02:32 PM Program Management User Story #116 (Closed): Procedure for Minors and Non-UofA Students working on projects
Nikhil Velagapudi

09/07/2023

03:27 AM Program Management User Story #306 (Closed): Key and Card Acquisition for AlbertaSat Project Room and Server Room
Nikhil Velagapudi

08/01/2023

05:54 PM CUBICS Phase #718 (New): Phase E: Operations and Sustainment
Phase E - Operation and sustainment. Starts with Deployment, ends with re-entry. Nikhil Velagapudi
05:53 PM CUBICS Phase #717 (New): Phase D: System Assemly, Integration, and Testing
Phase D: System Assembly, Integration and Testing. Ends in integration and subsequently launch. Nikhil Velagapudi
05:48 PM CUBICS Phase #716 (New): Phase C: Final Design and Fabrication Activities
Phase C - Final Design and Fabrication Activities. Ends in Internal CDR. Nikhil Velagapudi
05:47 PM CUBICS Phase #715 (In Progress): Phase B: Preliminary Design and Technology Completion Activities
Phase B - Preliminary Design and Technology Completion Activities. Ends in Internal PDR. Nikhil Velagapudi