Task #1474
openPhase #1392: Phase D: Assembly, Integration and Testing
Topic #1415: Engineering Model FlatSat
DFGM EM FlatSat Testing
Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
09/29/2025
Due date:
10/09/2025 (Due in about 3 months)
% Done:
0%
Estimated time:
Subsystem:
Systems
Success Criteria:
tests are complete
Updated by Priya Manavalan 22 days ago
- Due date changed from 06/24/2025 to 07/24/2025
- Start date changed from 06/12/2025 to 07/14/2025
- Follows Task #1465: DFGM + OBC added
- Follows Task #1458: DFGM + EPS added
Updated by Priya Manavalan 15 days ago
- Due date changed from 07/24/2025 to 10/09/2025
- Start date changed from 07/14/2025 to 09/29/2025
- Follows Task #1473: Iris EM FlatSat testing added