Actions
Task #1532
openPhase #1392: Phase D: Assembly, Integration and Testing
Topic #1415: Engineering Model FlatSat
Core EM FlatSat (UHF, OBC, EPS)
Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
07/07/2025
Due date:
07/07/2025 (Due in 19 days)
% Done:
0%
Estimated time:
Subsystem:
Systems
Success Criteria:
core flatsat tests are dione
Updated by Priya Manavalan about 13 hours ago
- Due date set to 06/26/2025
- Start date changed from 06/17/2025 to 06/26/2025
- Follows Task #1453: UHF Transceiver + EPS added
- Due date changed from 06/26/2025 to 07/07/2025
- Start date changed from 06/26/2025 to 07/07/2025
- Follows Task #1461: UHF Transceiver + OBC added
- Follows Task #1454: OBC + EPS added
Updated by Priya Manavalan about 13 hours ago
- Precedes Task #1470: Core EM FlatSat + Solar Panels + Heracles added
Updated by Priya Manavalan about 13 hours ago
- Precedes Task #1477: Core FM FlatSat: OBC + UHF + EPS added
Actions