Actions
Task #1532
openPhase #1392: Phase D: Assembly, Integration and Testing
Topic #1415: Engineering Model FlatSat
Core EM FlatSat (UHF, OBC, EPS)
Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
07/07/2025
Due date:
07/07/2025 (Due in 19 days)
% Done:
0%
Estimated time:
Subsystem:
Systems
Success Criteria:
core flatsat tests are dione
Actions