Task #1532

open

Phase #1392: Phase D: Assembly, Integration and Testing

Topic #1415: Engineering Model FlatSat

Core EM FlatSat (UHF, OBC, EPS)

Added by Priya Manavalan about 13 hours ago. Updated about 13 hours ago.

Status:
In Progress
Priority:
Normal
Assignee:
-
Start date:
07/07/2025
Due date:
07/07/2025 (Due in 19 days)
% Done:

0%

Estimated time:
Subsystem:
Systems
Success Criteria:
core flatsat tests are dione

Related issues 5 (5 open0 closed)

Follows Ex-Alta 3 - Task #1453: UHF Transceiver + EPSIn Progress06/18/202506/25/2025

Actions
Follows Ex-Alta 3 - Task #1461: UHF Transceiver + OBCIn Progress06/30/202507/04/2025

Actions
Follows Ex-Alta 3 - Task #1454: OBC + EPSIn Progress06/27/202507/04/2025

Actions
Precedes Ex-Alta 3 - Task #1470: Core EM FlatSat + Solar Panels + HeraclesIn Progress07/08/202507/15/2025

Actions
Precedes Ex-Alta 3 - Task #1477: Core FM FlatSat: OBC + UHF + EPSIn Progress07/08/202507/18/2025

Actions
Actions