User Story #93

closed

Northern SPIRIT - Feature #57: Operations Design

UHF Ground Station Rotor Calibration

Added by Nikhil Velagapudi about 2 years ago. Updated about 2 years ago.

Status:
Closed
Priority:
High
Start date:
03/05/2023
Due date:
04/12/2023
% Done:

0%

Estimated time:
1:00 h
Spent time:
Subsystem:
Success Criteria:
Actions #1

Updated by Priya Manavalan about 2 years ago

  • Priority changed from Normal to High
Actions #2

Updated by Nikhil Velagapudi about 2 years ago

  • Project changed from Northern SPIRIT to Sprint 117
  • Due date set to 04/12/2023
  • Subsystem deleted (Mission Design)

Get two new cameras and replace both

Actions #3

Updated by Pundeep Hundal about 2 years ago

  • Parent task set to #57
Actions #4

Updated by Nikhil Velagapudi about 2 years ago

  • Status changed from New to Closed
  • Estimated time set to 1:00 h
Actions