Phase #714

open

Phase A: Concept and Technology Development Activities

Added by Nikhil Velagapudi almost 2 years ago. Updated over 1 year ago.

Status:
In Progress
Priority:
Low
Start date:
03/07/2023
Due date:
10/27/2023 (about 18 months late)
% Done:

61%

Spent time:
(Total: 132:00 h)

Description

Phase A - Concept and Technology Development Activities. Ends in Internal MCR.


Subtasks 58 (27 open31 closed)

Feature #10: Requirements DefinitionNew03/07/202310/17/2023

Actions
Feature #45: Iris Preliminary Performance RequirementsNewLiam Droog03/07/202309/05/2023

Actions
Feature #125: Iris Science RequirementsNew03/07/2023

Actions
Feature #127: Iris Optical RequirementsNew03/07/2023

Actions
Feature #137: Iris Electronics RequirementsNew03/07/2023

Actions
Feature #281: Iris Mechanical RequirementsNew07/25/202309/05/2023

Actions
User Story #710: Iris optomechanics team kickoffClosedYeh-In Kang07/25/202308/31/2023

Actions
User Story #750: Getting project scope defined for Mec E 409 design projectClosedYeh-In Kang08/22/202309/05/2023

Actions
Sprint 011 - User Story #128: Iris Requirements Definition - Finish 1st DraftClosedPriya Manavalan07/11/202308/11/2023

Actions
User Story #130: Start and layout systems requirements tableClosedPundeep Hundal04/27/202305/02/2023

Actions
Sprint 010 - User Story #457: Requirements Definition Discussions - MechanicalClosedPundeep Hundal05/16/2023

Actions
Sprint 010 - User Story #458: Power Requirements Definition - Finish 1st DraftNewJoanne Cai07/11/202307/25/2023

Actions
Sprint 010 - User Story #459: Requirements Definition Discussions - System Wide & Embedded SystemsNewJoanne Cai05/16/2023

Actions
Sprint 010 - User Story #460: Requirements Definition Discussions - CommunicationNewHariharan Krishnan05/16/2023

Actions
User Story #461: Requirements Definition Discussions - ADCSClosedPundeep Hundal05/16/202307/18/2023

Actions
Sprint 010 - User Story #462: Requirements Definition Discussions - C&DHNewJoanne Cai05/16/2023

Actions
Sprint 008 - User Story #643: Reach out to NS System and set a meeting to discuss requirementsClosedPundeep Hundal06/27/202307/04/2023

Actions
Sprint 010 - User Story #683: ADCS Requirements Definition - Finish 1st DraftClosedPundeep Hundal07/11/202307/25/2023

Actions
Sprint 012 - User Story #768: System Requirements - Finalized for MCRNewJoanne Cai08/28/202308/30/2023

Actions
Sprint 012 - User Story #769: LEOP Requirements - Finalized for MCRNewJoanne Cai08/28/202308/30/2023

Actions
Sprint 012 - User Story #770: Embedded System Requirements - Finalized for MCRNewJoanne Cai08/28/202308/30/2023

Actions
User Story #771: Iris Payload Requirements - Finalized for MCRClosedYeh-In Kang08/28/202308/30/2023

Actions
Sprint 012 - User Story #772: DFGM/Corner Cube Payload Requirements - Finalized for MCRClosedPriya Manavalan08/28/202308/30/2023

Actions
User Story #773: ADCS Requirements - Finalized for MCRClosedRyan Bererton08/28/202308/30/2023

Actions
Sprint 012 - User Story #775: Software Requirements - Finalized for MCRNewDevin Headrick08/28/202308/30/2023

Actions
Sprint 012 - User Story #776: Power Requirements - Finalized for MCRClosedPriya Grewal08/28/202308/30/2023

Actions
Sprint 012 - User Story #777: Communications Requirements - Finalized for MCRClosedHariharan Krishnan08/28/202308/30/2023

Actions
Sprint 012 - User Story #778: Ground Segment Requirements - Finalized for MCRClosedHariharan Krishnan08/28/202308/30/2023

Actions
Sprint 012 - User Story #779: Operations Requirements - Finalized for MCRNewThomas Ganley08/28/202308/30/2023

Actions
Sprint 012 - User Story #801: Systems & Embedded Systems - Review comments on requirements from internal MCRNewJoanne Cai08/30/202309/04/2023

Actions
Sprint 012 - User Story #802: LEOP & Software - Review comments on requirements from internal MCRNewDevin Headrick08/30/202309/04/2023

Actions
Sprint 012 - User Story #806: Power - Review comments on requirements from internal MCRClosedPriya Grewal08/30/202309/04/2023

Actions
Sprint 014 - User Story #807: Communications and Ground Segment - Review comments on requirements from internal MCRNewHariharan Krishnan08/30/202309/04/2023

Actions
Sprint 012 - User Story #808: Operations - Review comments on requirements from internal MCRNewThomas Ganley08/30/202309/04/2023

Actions
Sprint 015 - User Story #891: Layout Systems Architecture DocumentNewJoanne Cai10/03/202310/17/2023

Actions
Sprint 015 - User Story #902: Draw first draft of system block diagramNewPundeep Hundal10/04/202310/17/2023

Actions
Feature #11: Requirements MaintenanceNew04/11/2023

Actions
Feature #84: Comms Knowledge TransferNew07/11/202308/31/2023

Actions
Feature #88: CONOPSIn ProgressPriya Manavalan03/21/202302/13/2024

Actions
User Story #282: Create Mission ObjectiveClosedPriya Manavalan03/26/202304/04/2023

Actions
User Story #283: First Draft STMClosedPriya Manavalan03/21/202304/15/2023

Actions
Sprint 009 - User Story #649: Finish section 3.1 of the Con-ops documentClosedPundeep Hundal07/11/202307/18/2023

Actions
Sprint 009 - User Story #657: Section 1.2.1ClosedSally Palmers06/27/202307/25/2023

Actions
Sprint 009 - User Story #660: Con Ops Section 3.3ClosedPriya Manavalan06/27/202307/18/2023

Actions
Sprint 009 - User Story #663: Con Ops Section 3.4ClosedMatthew Foran06/27/202307/25/2023

Actions
Sprint 009 - User Story #664: con ops section 3.5ClosedChristian Chenard06/27/202307/25/2023

Actions
Sprint 009 - User Story #667: con ops section 4ClosedParker Brambilla06/27/202307/25/2023

Actions
Sprint 010 - User Story #707: con ops commentsClosedSally Palmers07/25/202308/08/2023

Actions
Feature #448: Initial Project EstimatesNew05/16/202306/16/2023

Actions
User Story #449: First Draft CUBICS BudgetClosedPriya Manavalan05/16/202306/03/2023

Actions
Sprint 006 - User Story #520: KOM PrepClosedPriya Manavalan05/30/202306/02/2023

Actions
User Story #597: Finish revenue tab for the BudgetClosedPriya Manavalan06/13/202306/16/2023

Actions
Sprint 011 - Feature #600: Communication Subsystems Requirements ClosedHariharan Krishnan05/30/202307/18/2023

Actions
Feature #652: Project Risk AssessmentNewPriya Manavalan06/27/202311/14/2023

Actions
Sprint 008 - User Story #656: Create framework for project risk assesmentClosedPriya Manavalan06/27/202307/11/2023

Actions
Sprint 011 - User Story #682: Populate Internal Project Risks TabClosedPriya Manavalan07/11/202308/18/2023

Actions
Sprint 013 - User Story #827: Review and address Risk Matrix comments from Internal MCRClosedPriya Manavalan09/05/202309/12/2023

Actions
Sprint 016 - User Story #942: Update Risk Matrix based off MCR feedbackNewPriya Manavalan10/31/202311/14/2023

Actions
Actions #1

Updated by Nikhil Velagapudi almost 2 years ago

  • Subtask #652 added
Actions #2

Updated by Nikhil Velagapudi almost 2 years ago

  • Subtask #10 added
Actions #3

Updated by Nikhil Velagapudi almost 2 years ago

  • Subtask #11 added
Actions #4

Updated by Nikhil Velagapudi almost 2 years ago

  • Subtask #88 added
Actions #5

Updated by Nikhil Velagapudi almost 2 years ago

  • Subtask #448 added
Actions #6

Updated by Thomas Ganley almost 2 years ago

  • Subtask #600 added
Actions #7

Updated by Thomas Ganley almost 2 years ago

  • Subtask #84 added
Actions #8

Updated by Priya Manavalan over 1 year ago

  • Status changed from New to In Progress
Actions #9

Updated by Joanne Cai over 1 year ago

  • Due date changed from 11/14/2023 to 10/26/2023
Actions #10

Updated by Joanne Cai over 1 year ago

  • Due date changed from 10/26/2023 to 10/27/2023
Actions