Feature #819

closed

Phase #715: Phase B: Preliminary Design and Technology Completion Activities

Epic #977: Preliminary Designs and ICDs

Feature #1032: Preliminary Design: Hinges

Phase B - Deployable Research and Design

Added by Tyler Stocking over 1 year ago. Updated about 1 year ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Start date:
08/24/2023
Due date:
11/14/2023
% Done:

100%

Estimated time:
(Total: 60:00 h)
Spent time:
5:00 h (Total: 61:40 h)
Subsystem:
Mechanical

Description

This is the work relevant to the design of an initial prototype-compliant hinges, including research, rapid prototyping, CAD and manufacturing.


Subtasks 8 (0 open8 closed)

Sprint 012 - User Story #763: DRA application ClosedBen Harbarenko08/24/2023

Actions
Sprint 015 - User Story #878: Compliant Hyperion Hinge Preliminary Research ClosedSaksham Verma09/19/202310/03/2023

Actions
Sprint 015 - User Story #879: Compliant UHF Hinge Preliminary Research ClosedBrandon Martens09/19/202310/03/2023

Actions
Sprint 015 - User Story #880: Traditional UHF Hinge Preliminary Research ClosedAbegail Gagelonia09/19/202310/03/2023

Actions
Sprint 015 - User Story #882: Traditional Hyperion Hinge Preliminary Research ClosedSarah Keats09/19/202310/03/2023

Actions
User Story #915: Compliant Mechanism Concept Generation ClosedSaksham Verma10/16/202311/14/2023

Actions
User Story #916: Hyperion Hinge (Traditional) Concept Generation ClosedSarah Keats10/16/202311/14/2023

Actions
Sprint 016 - User Story #917: UHF Hinge (Traditional) Concept Generation ClosedAbegail Gagelonia10/17/202311/14/2023

Actions
Actions